Framework Agreement on purchase and renovation of Gas Turbine Meters
Energinet Forretningsservice A/S
Contract notice – utilities
Supplies
Section I: Contracting entity
National registration number: 39314797
Postal address: Tonne Kjærsvej 65
Town: Fredericia
NUTS code: DK032 Sydjylland
Postal code: 7000
Country: Denmark
Contact person: Procurement - K
E-mail: procurement@energinet.dk
Telephone: +45 70102244
Internet address(es):
Main address: https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
Address of the buyer profile: https://eu.eu-supply.com/ctm/Company/CompanyInformation/Index/228008
Section II: Object
Framework Agreement on purchase and renovation of Gas Turbine Meters
Through the establishment of the present Framework Agreement Energinet wants to purchase new gas turbine meters and renovations for our biogas stations. For further information see Appendix 2: Scope of Works. The procurement is conducted as a negotiated procedure and the Framework Agreement will be entered with one provider for the duration of 8 years.
N/A
Turbine meters are used in more than 50 metering stations owned by the Danish national TSO - Energinet. These turbine meters are used for metering natural gas flow. The turbine meters are replaced or renovated with regular intervals.
This framework agreement regards a single producer or supplier (Seller) of Gas turbine meters for purchase of new turbine meters and renovation/refurbishing of Seller’s own brands of turbine meters.
For further information see Appendix 2: Scope of Works.
The framework agreement is tendered by Forretningsservice A/S (part of the Energinet Group). Forretningsservice A/S serves as a central purchasing body awarding the framework agreement on behalf of Teknik og Anlæg A/S (part of the Energinet Group). Further information is available in the Tender Documents.
The procurement is conducted as a negotiated procedure and the framework agreement will be entered with one provider for the duration of 8 years.
If more than 3 applicants fulfil the minimum requirements, cf. section III, the Contracting Authority will prequalify the 3 applicants who are evaluated as most qualified for the specific tendered assignment. Only these applicants will be invited to submit a tender. The selection of the applicants will be based on the submitted references. That is to which extend the reference(s) are assessed to be similar to the tendered assignment, cf. section II.2.4, in terms of comparability and relevance. As a result, the number of references will not be the determining factor alone, but more importantly to which degree the specific forwarded references are comparable and relevant to the tendered assignment regarding solution and scope. The following will in particular be rated positively:
• Extensive experience in supplying turbine meters for the gas and biogas industry.
• Extensive experience in supplying turbine meters with detection of gas in both directions.
Companies in which Energinet SOV or another company in the Energinet group acquire half or more than half of the capital or have the authority to exercise half or more than half of the voting rights or has the right to manage the company’s business regardless of the official name during the term of the Framework Agreement will have an option to use the Framework Agreement.The Framework Agreement can be expanded 2 times with 20 percent of the value of the Framework Agreement as stated in the tender notice, in cases where the circumstances for the scope of the Framework Agreement have changed from the time of the conclusion of the tender, cf. Framework Agreement sub-section 9.2.
Please note that this is a negotiated procedure. Except for mandatory parts, the Tender Documents may as a result undergo changes as part of the negotiation process. For elements explicitly identified as subject to negotiation which may lead to changes made by the Contracting Authority in the negotiation process, see section 3.7.1. in Tender Conditions.
Section III: Legal, economic, financial and technical information
The applicant must confirm the economic ability in the ESPD part IV.B: “Economic and financial standing” with information - from the latest annual report at the submission date for prequalification - regarding the following economic indicators:
1. Equity (total equity incl. share capital, reserves, revaluation, retained earning etc.)
2. Equity ratio (equity/total assets)
If the applicant is relying on the capacities of one or more other entities (e.g., a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g., a consor-tium) the information for the ESPD part IV.B must also be given in a separate ESPD from each of these entities, cf. section VI.3 “Additional information”. It is the sole responsibility of the appli-cant to secure that the minimum level(s) of standards required are reached on the basis of consolidation when the applicant is relying on the capacity of other entities or when the appli-cant is a group of economic operators (e.g., a consortium).
Concerning 1: Equity from the latest annual report must be at least EUR 288.750.
Concerning 2: Equity ratio from the latest annual report must be at least 20 pct. If the equity ratio is between 15 pct. and 20 pct. the applicant can qualify if Equity exceeds EUR 875.000.
The applicant must include the up to 5 most comparable and relevant references undertaken in the past three (3) years as part of the application.
The references must be stated in the ESPD part IV.C: “Technical and professional ability”. Undertaken in the past three (3) years implies that the reference must not have been completed prior to the date reached when counting 3 years backwards from the submission date for prequalification. References older than this will not be taken into consideration. References which have not yet been fully completed can be included as part of the application, but if this is the case, the applicant must describe the parts which have not yet been delivered, and this may affect the evaluation of the applicant, cf. section II.2.9.
The references should include a specific description of the work performed for each reference, including:
1. The supplied turbine meter type/brand/name and what industry the turbine meter was supplied to (oil, natural gas, or biogas industry).
2. The supplied turbine meters characteristics regarding detection of gas in both directions.
3. The number of years the tenderer has supplied turbine meters to the customer mentioned in the reference, also under previous contracts.
4. Any other relevant description regarding the extent of experience in connection to the similarity of the tendered assignment, cf. section II.2.4.
5. Contract value (if possible)
6. Contact information for the entity in question (if possible, including contact person)
7. Date of initiation and final delivery (day, month, year)
Any ambiguities and/or incomprehensibilities concerning the above information may have a negative effect on the selection of candidates, cf. section II.2.9. Please note the “description” box can contain more text than is visible. I.e., it is possible to copy paste text into the box.
If the applicant is relying on the references of one or more other entities (e.g., a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g., a consortium) the information for the ESPD part IV.C must also be given in a separate ESPD from each of these entities.
The number of references should not surpass a maximum of the 5 most comparable and relevant references. If the applicant is relying on the capacity of one or more other entities (e.g., a parent or sister company or a subcontractor) or the applicant is a group of economic operators (e.g., a consortium) the maximum number of references to be submitted must still be respected and cannot exceed 5 when combined. If more than 5 references are submitted, the Contracting Authority will only consider the 5 biggest references determined by contract value.
The applicant must submit minimum
• One (1) reference documenting supply of fiscal gas turbine meters for the gas or bio-gas industry.
The applicant must submit a completed version of the ESPD.
Applicants may not be subject to the mandatory grounds for exclusion, cf. the Danish Public Procurement Act (udbudsloven) Section 135 (1-3) and 136.
Please see section VI.3 “Additional information” for further information regarding the ESPD. The application must be submitted through EU-Supply, cf. link in section I.1 in this TED announcement. Applications not submitted via EU-Supply or received after the deadline will not be accepted.
The Contracting Authority reserves the right to request the applicant to supplement, specify or complete the information submitted.
The information is stated in the Tender Documents.
The information is stated in the Tender Documents.
The information is stated in the Tender Documents.
The information is stated in the Tender Documents.
Section IV: Procedure
Section VI: Complementary information
The applicant must submit a completed ESPD to apply for prequalification for this tender procedure. The ESPD for this tender can be found via EU-supply. The ESPD must be completed in EU-Supply and submitted via “My Response”.
Please note:
- An applicant participating on its own, but relying on the capacities of one or more other entities (e.g. a parent or sister company or a subcontractor), must ensure that the application includes the applicant's own ESPD together with a separate ESPD from each of the entities it relies on with a completed part II: “Information concerning the economic oper-ator” and part III: “Exclusion grounds” of the ESPD as well as the relevant information regarding part IV: “Selection criteria” and part V: “Reduction of the number of qualified candidates”. The ESPD from each of the entities should be duly filled and signed by the entities concerned.
Further where an applicant wants to rely on the capacities of other entities, it shall prove to the contracting authority that it will have at its disposal the resources necessary, for example, by producing a commitment by those entities to that effect, which must be submitted as part of the final documentation .
- Where groups of economic operators, including temporary associations, participate together in the procurement procedure, a complete separate ESPD for each of the partic-ipating economic operators must be submitted.
Further the final documentation must include a signed declaration by all parties of the group of economic operators (joint venture, consortium or other) stating that all economic operators assume joint and several liabilities towards the Contracting Authority for the performance of the contract as a whole.
Postal address: Nævnenes Hus, Toldboden 2
Town: Viborg
Postal code: 8800
Country: Denmark
E-mail: klfu@naevneneshus.dk
Telephone: +45 72405708
Internet address: https://naevneneshus.dk/start-din-klage/klagenaevnet-for-udbud/
Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification in-cludes a short account of the relevant reasons for the decision.
Other complaints must be filed with The Complaints Board for Public Procurement within:
1. 45 calendar days after the contracting authority has published a contract award no-tice in the Official Journal of the European Union (with effect from the day following the publication date);
2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the rel-evant reasons for the decision;
3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Postal address: Carl Jacobsen Vej 35
Town: Valby
Postal code: 2500
Country: Denmark
E-mail: kfst@kfst.dk
Telephone: +45 41715000
Internet address: http://www.kfst.dk