170 kV GIS for Kriegers Flak Combined Grid Solution offshore


Energinet.dk

Corrigendum

Notice for changes or additional information

Supplies

(Supplement to the Official Journal of the European Union, 2016/S 044-072061)

Section I: Contracting authority/entity

I.1) Name and addresses
Energinet.dk
28980671
Tonne Kjærsvej 65
Fredericia
7000
DENMARK
Telephone: +45 70102244
E-mail: procurement@energinet.dk
Fax: +45 76245180
NUTS code: DK

Internet address(es):

Main address: www.energinet.dk/tenders

I.1) Name and addresses
50Hertz Transmission GmbH
Eichenstrasse 3A
Berlin
12435
GERMANY
E-mail: purchasing@50hertz.com
NUTS code: DE3

Internet address(es):

Main address: www.50hertz.com

Section II: Object

II.1) Scope of the procurement
II.1.1) Title:

 

170 kV GIS for Kriegers Flak Combined Grid Solution offshore.

 

Reference number: 15/11469
II.1.2) Main CPV code
31000000
II.1.3) Type of contract
Supplies
II.1.4) Short description:

 

The scope of work include in particular design, fabrication, delivery, installation, inspection, testing and commissioning of one 170 kV, 50 Hz, gas insulated switchgear (GIS) for an offshore substation.

Delivery of equipment is foreseen for Q3 2017. Subject to change of time-plan.

 

Section VI: Complementary information

VI.5) Date of dispatch of this notice:
15/03/2016
VI.6) Original notice reference
Notice number in the OJ S: 2016/S 044-072061

Section VII: Changes

VII.1) Information to be changed or added
VII.1.2) Text to be corrected in the original notice
Section number: III.1.3)
Place of text to be modified: Technical and professional ability
Instead of:

 

c) he doesn't declare that if factory repairs are required, the transformer will be transported from the quay to the factory where the repairs will be performed, a receiving inspection and test will be performed in the test facility, the active part will be removed from the tank and a report on the receiving inspection will be submitted, all within 8 weeks. Within the warranty period all costs resulting from the defect be at the contractor's expense.

 

Read:

 

c) he doesn't declare that if factory repairs are required, the GIS will be transported from the quay to the factory where the repairs will be performed, a receiving inspection and test will be performed in the test facility,the active part will be removed from the tank and a report on the receiving inspection will be submitted, all within 8 weeks. Within the warranty period all costs resulting from the defect be at the contractor's expense.

 

VII.2) Other additional information: