Fakta om udbudet
Udbyder
DONG Energy Thermal Power A/S
ASV6 Lot 6 DCS (Overall System)
DONG Energy Thermal Power A/S
Corrigendum
Notice for changes or additional information
Services
(Supplement to the Official Journal of the European Union, 2016/S 209-379010)
Section I: Contracting authority/entity
DK
Kraftværkvej 53
Fredericia
7000
Denmark
Contact person: DONG Energy Thermal Power A/S
Telephone: +45 99552843
E-mail: nanve@dongenergy.dk
NUTS code: DK042
Internet address(es):
Main address: http://www.dongenergy.com
Section II: Object
ASV6 Lot 6 DCS (Overall System).
The scope of Works for LOT 6 includes the design, engineering, programming, supply, erection, testing, commissioning and documentation of the Contract Object, an Overall, main, DCS system for ASV6 incl. overall project management for Lot 6.
For a more detailed description of the scope of works for LOT 6, see section VI.3) Additional Information.
Section VI: Complementary information
Section VII: Changes
(...)
1. Financial and economic capacity: 30 %
2. References: 50 %
3. Quality Management: 10 %
Ad1) Financial and economic capacity: 30 %
The assessment regarding the Applicant's economic and financial capacity will be based upon the figures requested in section III.1.2) submitted by the Applicant in the ESPD.
Ad 2) References
The assessment regarding the Applicant's References will be based upon the information requested in section III.1.3) last section, submitted by the Applicant in the ESPD.
Ad3) Quality Management System:
The assessment regarding the Applicant's Quality Management System will be based upon the informations requested in section III.1.3) first section regarding Quality Management, submitted by the Applicant in the ESPD.
(...)
1. Financial and economic capacity: 30 %
2. References: 55 %
3. Quality Management: 15 %
Ad1) Financial and economic capacity: 30 %
The assessment regarding the Applicant's economic and financial capacity will be based upon the figures requested in section III.1.2) submitted by the Applicant in the ESPD.
Ad 2) References. 55 %
The assessment regarding the Applicant's References will be based upon the information requested in sectionIII.1.3) last section, submitted by the Applicant in the ESPD.
Ad3) Quality Management System: 15 %
The assessment regarding the Applicant's Quality Management System will be based upon the informatoins requested in section III.1.3) first section regarding Quality Management, submitted by the Applicant in the ESPD.
Beside the above correction of II.2.9, the remaining part of section II.2.9 as inserted below are still valid.
Envisaged minimum number: 3
Maximum number: 5
Objective criteria for choosing the limited number of candidates:
Applicants must have a financial strength proportionate to the magnitude of the Contract in order to ensure proper performance, and the necessary technical capacity to ensure proper fulfilment of the contract.
If the number of Applicants applying for prequalification exceeds 3-5, the Contracting Entity will perform the prequalification on the basis of an evaluation of the following criteria with the weighting as specified: